Industry · Metal fabrication

Job costing for metal fabrication shops in Odoo

Every job is custom, so the only cost that matters is the cost of that job. How to set up Odoo so an accepted quote becomes a job, and the finished job carries an actual cost you can hold against the estimate.

By Octagotech Team8 min read

Key takeaways

  • A confirmed quote opens a manufacturing order, so every cost lands on one job record.
  • Operations and work center hourly rates turn logged time into labor cost per job.
  • Usable drops return to stock as by-products and can take a share of the job's cost.
  • Outside processing runs through standard Subcontracting, with the vendor's charge on the job.
  • Nesting stays in your CAM software; Odoo records what the nest consumed.
  • Analytic accounts put each job's revenue and cost side by side in accounting.

A fab shop does not have a product cost. It has a job cost, and it is different every time. Two brackets that look alike on a drawing can use different plate, a different nest, twice the weld time and a different trip to the galvanizer. If the only cost anyone sees is the estimator's spreadsheet, you learn which jobs lost money when the books close, weeks too late to act.

This guide walks through job costing in Odoo from the quote to the actual cost on the finished job, using the settings we configure on Odoo projects for fab shops. It assumes you know Odoo basics; for the wider picture, start with our Odoo MRP guide.

The job is the manufacturing order

In Odoo, the unit of job costing is the manufacturing order (MO). It holds the components consumed, a work order per operation with the time logged against it, any by-products and any scrap. When the MO is marked done, Odoo values the finished parts from those actuals.

Three settings decide whether that works: products made to order, bills of materials (BOMs) with operations, and work centers with real hourly rates. Get those right and cost builds up as the floor works, instead of being rebuilt from timecards at month-end.

From quote to job

A job starts as a quotation in the Sales app, with the customer's drawings attached. Give the product the Manufacture route plus make-to-order, and confirming the sales order creates an MO linked to it. The MO shows the sales order as its source and the order links back to the MO, so anyone can move from the customer's PO number to the job on the floor in one click.

Material bought for one job works the same way. Set a special component, say a heavy-wall tube you never stock, to Buy plus make-to-order, and confirming the MO drafts a purchase order for exactly what that job needs. Stock plate and bar stay on reorder rules.

For the quote, the BOM overview report rolls component cost and operation time up into a cost per unit, and a pricelist rule can apply your markup to cost. That puts the estimate on the same basis as the actual cost you will compare it with later.

A BOM and routing for every job

Repeat parts are simple: one BOM, reused on every order. One-off jobs need a decision between two workable patterns.

The first is a product and BOM per job: the estimator copies the closest template BOM, adjusts material and operations, and saves it under the job number. It means more records, but each job keeps its own planned material and times to compare against. The second is a family BOM that the planner edits on the draft MO for this job only. It keeps the product list short, but the estimate then lives only on that MO. Mostly custom shops tend to choose the first; shops with families of similar parts, the second.

Operations, which older Odoo versions called routings, sit on the BOM. Each names a work center (saw, laser, press brake, weld cell, paint line) and an expected time. Set that time from your estimating standards, or let Odoo compute it from the time logged on recent work orders, which keeps repeat-part estimates honest without a spreadsheet.

Decide early whether plate and bar are stocked by the sheet, by weight, by area or by length. It changes how remnants are counted, and changing it after go-live means recounting stock.

Time at the work center

Labor is where paper travelers lose the most information. Each work center in Odoo carries a cost per hour, setup and cleanup times, and an efficiency factor. Every work order records who worked on it and for how long, and that duration times the work center rate becomes the labor cost on the job.

How operators log time depends on the edition. In Community, work orders are started, paused and finished from the MO in the backend, which works if a lead records time for the crew. In Enterprise, the Shop Floor app puts a job queue on a tablet at each work center: the welder taps the next job, starts the timer and closes it when done. For a shop that wants real labor cost per job, Shop Floor is often the deciding reason to choose Enterprise; our Community vs Enterprise evaluation covers the rest of that trade-off.

Decide what the work center rate includes. Some shops load machine cost, wages and overhead into one rate. Others keep a machine rate and let Enterprise add each operator's hourly cost when they sign in to Shop Floor as an employee. Either works; mixing both without a rule counts labor twice.

Material, drops and remnants

Odoo does not nest parts; that stays in your CAM or nesting software. What Odoo records is the result: which sheet or bar was consumed, by lot, and what came back.

With heat numbers recorded as lot numbers at receiving, the operator, or the planner working from the nest report, records the actual sheet consumed on the MO. With automated inventory valuation, that sheet is costed at what you paid under FIFO or average cost, not at a standard. If the job used more than planned, the BOM's consumption setting decides whether that is allowed, allowed with a warning, or blocked. Plate spoiled at fit-up goes through the Scrap button on the MO, so it shows as scrap on this job rather than vanishing into a count adjustment.

Usable drops go back to stock as by-products. Add a remnant product to the BOM (a plate drop in the same grade and thickness, for example) and record it at the cutting operation with its own lot, carrying the heat number forward. Buyers then see the drop before ordering new plate.

A by-product can also take a cost share: a percentage of the job's cost that moves onto the remnant. Without it, a job that leaves a good half sheet carries the cost of the whole sheet, and the next job gets the drop free. Keep the rule simple enough that people apply it every time.

Where Odoo stops. Nesting, part programs and machine code stay in CAM. Importing the nest's material usage straight into the MO is an integration, not a standard feature, and it pays off only at volume.

Outside processing without losing the part

Galvanizing, plating, powder coat and heat treat are where parts leave the building and, in most shops, the system too. Subcontracting, part of standard Inventory and Manufacturing, keeps them on the books.

The pattern is to split the part in two. "Frame, welded" is made in-house on its own BOM. "Frame, galvanized" has a subcontracting BOM, with the welded frame as its component and the galvanizer as subcontractor. A purchase order to the galvanizer tells Odoo to expect galvanized frames back, a resupply transfer ships the welded frames out, and the receipt consumes one and stocks the other. While the parts are out, they sit in the subcontractor's location, so you can see what is at which vendor.

The galvanized frame is valued at the cost of the welded frame plus the price on the purchase order, so the vendor's charge lands on the job without re-keying. If the galvanizer bills by weight and the bill differs from the PO, match it against the PO so the difference is flagged for review (automatic three-way matching needs Enterprise).

Estimated against actual

When the MO is done, compare. The MO's overview shows expected cost beside real cost for components and operations, and work order reporting shows planned against real duration by work center.

Take a hypothetical 40-person job shop that quotes 24 welded and galvanized brackets at $4,800, from a family BOM with laser cutting, forming, welding and outside galvanizing.

Cost lineEstimatedActualWhat moved
Plate and bar$1,850$1,910Heavier sheet substituted from stock
Laser cutting$240 (2.0 h at $120)$300 (2.5 h)Extra pierce time on thicker plate
Forming$135 (1.5 h at $90)$135 (1.5 h)On plan
Welding$850 (10 h at $85)$1,105 (13 h)Fit-up rework on six parts
Galvanizing$480$525Billed by weight
Total cost$3,555$3,975$420 over, about 12%
Margin on $4,800$1,245 (26%)$825 (17%)Nine points of margin lost

Hypothetical figures for illustration only.

The total says the job made less than planned. The lines say why: welding ran three hours over, and the reason is on the work orders. That is the conversation to have with the estimator and the weld lead, and it is only possible when time was logged against the job as it happened.

Close MOs promptly, so a job's time is not mixed across months, and review variance by work center as well as by job: a cell that always runs over has a rate or standards problem.

Where accounting fits: analytic accounts

The MO gives you production cost. The owner wants to know what the job made, which needs revenue and sometimes costs that never touch the MO, such as installation, freight or a design fee. That is what analytic accounts are for.

Create one analytic account per job, or per customer project if a project spans several jobs, and put it on the sales order lines, the MO and the purchase orders for job material and outside work. Depending on your Odoo version, the MO takes the analytic account directly or through a linked project. Invoice revenue, MO material and labor, and vendor bills then post to the same analytic account, and the analytic report shows revenue against cost per job.

Behind that, automated inventory valuation posts journal entries as stock moves, so the value of plate in the rack matches the balance sheet. Jobs that span a month-end raise a work-in-progress question: agree with your accountant how open jobs are valued before go-live, not at the first close.

Common questions

Can Odoo quote a job from its BOM and routing?

Yes. The BOM overview rolls component cost and operation time up into a cost per unit, and a pricelist rule can apply your markup to cost. Many shops price one-off jobs from a template BOM copied for each job.

Does job costing in Odoo need Enterprise?

No. Manufacturing orders, operations, work center rates, by-products, subcontracting and analytic accounts are all in Community. Enterprise adds the Shop Floor tablet app, which is how most shops capture operator time reliably, plus Quality checks per operation and the Barcode app.

How are remnants valued in Odoo?

Record usable drops as by-products of the cutting operation, each with its own lot. A by-product can carry a cost share, a percentage of the job's cost moved onto the remnant, so the next job that uses it pays for it.


We have not published a fab-shop case study yet. The closest is a custom-parts manufacturer that moved 340 BOMs and 12 work centers into Odoo MRP in 14 weeks, described in our Odoo MRP case study. If you are scoping an Odoo implementation for your shop, bring your routing list with work center rates, your outside processors and one job you think lost money, and we will walk that job through Odoo with you. Book a discovery call.

Octagotech Team

Certified Odoo Ready partner · San Francisco, New York, Ahmedabad and Rajkot

We write from live Odoo engagements: 20+ implementations over 5+ years. About Octagotech.

Know what every job really cost.

Bring your routing list, your outside processors and one job you think lost money. The first call takes 30 minutes.

Or email sales@octagotech.com