Mondays went to planning
The production manager spent the first half of every Monday collating open orders, stock, and machine capacity by hand.
Case study · Manufacturing
A custom parts manufacturer was planning production in spreadsheets and WhatsApp. In 14 weeks we moved its BOMs, capacity, and replenishment into Odoo MRP.
Results at 90 days
Before · 85 employees, one facility
Production planning ran entirely on spreadsheets and WhatsApp messages. The week's schedule was usually ready by Wednesday.
The production manager spent the first half of every Monday collating open orders, stock, and machine capacity by hand.
With the schedule landing midweek, the shop worked without a plan three days out of every five.
Materials bought outside normal procurement cycles cost the company 15–22% more.
Shortages caused partial shipments and customer penalties.
Discovery
Discovery documented three root causes, and one earlier attempt to fix them that had failed.
There was no automated chain from customer demand through the BOM to components.
Scheduling ran on the planner's experience, not on data about machines and shifts.
Reorders happened after a shortage showed up, not before it.
QuickBooks had no manufacturing modules. An add-on MRP tried two years earlier was dropped after three months because it needed every inventory transaction entered twice.
14 weeks · five phases
Master data first, then capacity, then the planning logic, then a parallel run before cutover.
We exported 340 BOMs from the Access database, checked them against actual shop-floor usage, and imported them into Odoo Manufacturing with correct component quantities and yield factors.
All 12 work centers modeled with real capacity, shift patterns, and downtime allowances. Routings for each product family, plus a shop-floor tablet view for operators to start and finish work orders.
Make-to-order and make-to-stock set by product category. Reorder rules with safety stock based on 12 months of usage history, feeding automated purchase orders.
Quality control points at three key work-center stages, and a production dashboard showing WIP, work-order backlog, and daily output against target.
Two weeks of parallel running with production orders entered in both systems, and training by role. Go-live was the Monday of week 14, with our team on site through that week's production cycle.
Tell us how your shop plans today. We will scope the MRP project in a 30-minute call.
Book a discovery callMeasured after go-live
| Area | Before | With Odoo, configured by us |
|---|---|---|
| Weekly schedule | Built by hand, ready by Wednesday | MRP runs overnight; exceptions approved each morning |
| Bills of materials | A separate Access database | 340 BOMs in Odoo, checked against usage |
| Capacity | Scheduled from experience | 12 work centers with shifts and downtime |
| Low stock | Found after the shortage | Caught 6 days before a halt, on average |
| Shop floor | Updates by WhatsApp | Work orders started and finished on tablets |
Odoo apps
Six Odoo apps on one database, in place of QuickBooks and spreadsheets.
Keep going
Multi-level BOMs, routings, work centers, make-to-order and make-to-stock, and real-time costing.
Odoo for manufacturing ServiceBOMs, routings, work centers, costing, and scheduling configured to how your shop actually runs.
Odoo manufacturing consulting ArticleBOMs, work centers, shop-floor control, quality, and subcontracting in one guide.
Odoo MRP guide
The first call takes 30 minutes.
Or email sales@octagotech.com